NOTICE OF WATER LINE REPLACEMENT CONSTRUCTION SUMMER 2019 AFFECTING STAGECOACH DRIVE

PLEASE BE AWARE OF THE FOLLOWING WATER LINE REPLACEMENT PROJECT ON STAGECOACH DRIVE. THE PROJECT WILL PROCEED IN FOUR PHASES FROM APPROXIMATELY JUNE 17TH THROUGH AUGUST 15TH AND WILL AFFECT SEVERAL INTERSECTIONS ALONG STAGECOACH DRIVE:

1. Phase I – Intersection of Blacksmith Drive and Stagecoach Drive south to intersection with Ecker Hill Drive – Approximately one week.

2. Phase II – Intersection of Ecker Hill Drive and Stagecoach Drive to intersection with Pack Saddle Circle – Approximately one week.

3. Phase III – Intersection of Pack Saddle Circle and Stagecoach Drive to the midway “point” of Stagecoach Drive – Approximately three weeks.

4. Phase IV – Midway “point” of Stagecoach Drive to intersection of Stagecoach Drive and Buckboard Drive by the pickleball court and park – Approximately three weeks.

Water service during the project will be interrupted, but durations should be minimal and as much advanced warning as possible will be provided to the affected homes. Please plan accordingly and allow additional drive time during the project. We also suggest familiarizing yourself with alternate routes through Pinebrook before construction begins. Local residential access will be allowed at all times to homes within the construction areas. Please check our website at www.gorgozawater.com for updates and additional information during the construction period. Water line replacement is a necessary and vital component of maintaining the integrity of your water system. We apologize for any inconvenience these projects may cause and thank you in advance for your patience and understanding. If you have any questions or concerns, please contact our office at 435-649-7948.